FLCC Paving Project Update

Here we will post the status updates on the paving Project.

5/13/21

The back-filling of the roads are almost complete.

5/2/21

Work is almost done! We will be doing some additional wok back-filling the drop-off on the side of the roads where the asphalt was overlaid.

Photos: Sam Fox

4/23/21

 

Work continues. The nights have been cold and there has been some rainy days. We hope to have one more update before opening day.

Photo: Jim Nicoletti

 

Photos: Joanne Reinhardt

 

 

4/12/21

Milling has started. They have been working on Azalea, Buttercup and Carnation.

Currently we are scheduled to be complete the project by May 3. The weather may have an impact in this date. No major issues thus far. Where the roads are being dug, we are taking the opportunity to make some pipe repairs. Bill and Rod are adding protective sleeves to the piping for added protection.
This week calls for damp and wet weather so we may lose a little time.

Photos : Sam Fox

 

4/2/21
Transport the following pieces of equipment to site location.
Cat 430 IT backhoe,
Tru Pac 915 roller,
Cat skidsteer.
4/5/21
Move in milling machine, mark out all roads to be milled and place millings on site. Address all water runoff, compact subbase and truck in item 4.
Briggs Paving will update schedule throughout production duration.